Contact Us to Speak to an Attorney (562) 375-7975

Blog

Constructive Change in Construction Projects: What Contractors Need to Know

Posted by Dan Phelps | Jun 09, 2026 | 0 Comments

I.   Introduction

Construction projects rarely proceed exactly as planned. Plans evolve, schedules shift, and field conditions change. But at some point, changes can cross a legal line. When that happens, contractors may have rights beyond the contract's written terms. One of the most important, but often misunderstood, concepts is constructive change.

This article explains constructive change, how it differs from related doctrines under California and federal law, and why it matters to contractors.

II.  What Is a Constructive Change?

A constructive change occurs when a contractor is required to perform work beyond the contract requirements, even though no formal change order was issued. This can happen through:

·         Being told verbally to perform additional work

·         Being forced to work out of sequence because other trades are not ready

·         Being required to adjust methods due to missing or defective plans

·         Being placed in conditions that make the original plan impossible

Under federal law, constructive change is well-established. It applies when a contractor performs extra work due to the other party's direction or fault, even without a formal modification. [1]

California does not formally recognize “constructive change” as a standalone doctrine. But the same conduct is analyzed under traditional contract principles, like breach of contract. [2]

In simple terms, a constructive change means: “You were made to do more than you signed up for, even if no one formally said so on paper.”

III.  Why Constructive Change Matters

Most construction contracts require written change orders. But projects rarely operate that cleanly. Owners and general contractors often:

·         Give instructions in the field

·         Expect immediate compliance

·         Delay or avoid issuing formal change orders

The law recognizes this reality. Even when a contract requires written approval:

·         A contractor may still recover for extra work

·         Courts may find that formal requirements were waived by conduct

·         The absence of paperwork does not automatically defeat a claim[3]

The key question is not whether the paperwork exists, but whether the contractor performed work outside the agreed scope due to the other party's conduct.

IV.             The Relationship with Other Doctrines

Constructive change rarely exists in isolation. It is part of a larger legal framework that includes cardinal change and contract abandonment.

A.                Cardinal Change (Primarily Federal)

A cardinal change occurs when modifications are so extensive that they fundamentally alter the nature of the contract. When that happens:

·         The work is no longer within the original agreement

·         The change becomes a breach, not a modification[4]

California courts have discussed this concept but have not formally adopted it as an independent doctrine. [5]

B.                 Contract Abandonment (California)

California law provides a powerful related concept: abandonment. This occurs when:

·         Changes are so extensive that the parties are no longer operating under the contract

·         Both parties, through conduct, depart from the contract's framework

When abandonment is found:

·         The contract's limitations (including pricing and procedural rules) no longer apply

·         The contractor may recover the reasonable value of the work performed[6]

C.                How Constructive Change Fits

Constructive changes often serve as the building blocks of larger claims:

·         Individual constructive changes → may support extra-work claims

·         Numerous constructive changes → may support abandonment or cardinal change

V.                Common Fact Patterns

Courts repeatedly recognize constructive changes in situations such as:

·         Being required to work out of sequence due to coordination failures

·         Performing additional tasks not included in the original scope

·         Adjusting work methods because site conditions were not as represented

·         Following informal directives from authorized personnel

In each case, the contractor performs differently than originally agreed, not by choice, but because of the other party's conduct.

VI.             Effect on Contractual Limitations

Constructive change does not automatically invalidate contract provisions. But it can significantly affect how they are applied.

VII.          Written Change Order Requirements

Even if a contract requires written change orders:

·         Repeated informal directives (oral change orders) may constitute a waiver of that requirement

·         Courts focus on the parties' actual course of conduct³, not just the contract requirements

VIII.       No-Damages-for-Delay Clauses

These clauses are generally enforceable in California on private works of improvement, but with important exceptions. They do not apply when delays result from:

·         Active interference

·         Uncontemplated conditions

·         Fundamental breaches of obligation[7]

If the conduct giving rise to constructive changes also causes delay, these exceptions may allow recovery.

IX. Practical Takeaways for Contractors

  1. Document Everything
    Even if directives are informal, maintain records of instructions, conditions, and impacts.
  2. Identify Scope Changes Early
    Distinguish between minor adjustments and work that goes beyond the contract.
  3. Preserve Your Rights
    Continue performance if required but clearly communicate that the work is extra.
  4. Track Cumulative Impact
    Individual changes may seem small, but their combined effect can support larger claims.
  5. Understanding the Legal Framework
    Constructive change is not just about extra work; it may lead to broader remedies under California law.
X.                Conclusion

Constructive change reflects a simple principle: contracts should not be used to avoid paying for work that was never agreed to.

Federal law recognizes this through a formal doctrine. California law reaches the same result through related concepts like breach, abandonment, and quantum meruit.

For contractors, the lesson is clear: when a project begins to diverge from the plan, the law may provide remedies, even if the contract says otherwise.

Footnotes 


[1] Bruner & O'Connor on Construction Law § 4:25.

[2] Amelco Electric v. City of Thousand Oaks, 27 Cal. 4th 228.

[3] 9 Cal. Real Est. § 31:66 (Miller & Starr).

[4] Krygoski Constr. Co. v. United States, 94 F.3d 1537 (Fed. Cir. 1996).

[5] Amelco Electric v. City of Thousand Oaks, 27 Cal. 4th 228, 239–42.

[6] C. Norman Peterson Co. v. Container Corp. of America, 172 Cal. App. 3d 628.

[7] Howard Contracting, Inc. v. G.A. MacDonald Constr. Co., 71 Cal. App. 4th 38; Hawley v. Orange County Flood Control Dist., 211 Cal. App. 2d 708.

At Phelps Law Corp, we focus exclusively on construction law and represent contractors, subcontractors, owners, and suppliers throughout California in complex construction disputes. The issues discussed in this article, constructive changes, extra work, delays, and scope modifications are among the most common claims we see on construction projects. We generally handle construction claims exceeding $100,000, where strategic claim development and litigation can have a significant financial impact. If your project has involved unpaid extra work, project disruption, or changes beyond the original scope, our firm can evaluate your rights and help pursue the compensation you are owed.

About the Author

Dan  Phelps
Dan Phelps

Daniel J. Phelps is a contractor and construction attorney.  His practice is focused on litigating construction contract claims. For more than 40 years he has been dedicated to the construction industry.  He has years of experience working on claims arising out of construction projects. Mr. Ph...

Comments

There are no comments for this post. Be the first and Add your Comment below.

Leave a Comment

A Law Practice Engineered for Construction

We utilize construction professionals. Our Construction Attorney works with an exceptional team of construction professionals, engineers, and construction managers to provide an efficient and cost effective approach to your legal needs. You won't be paying for an associate attorney to learn how to read plans and understand how RFIs impact time and expense. Those tasks are performed by people with construction backgrounds. Call us to discuss your legal needs.

Menu